Question
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is:
Solution
Ans.4
A’s 1 day’s work = 1/15
B’s 1 day’s work =1/20
(A + B)’s 1 day’s work = [1/15+1/20] = 7/60
(A + B)’s 4 day’s work = [7/60 × 4] = 7/15
Therefore, Remaining work = [1 ? 7/15 ] = 8/15
Ans.4