Question
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days, with help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution
Ans.3
(A + B + C)’s 1 day’s work =1/4
A’s 1 day’s work =1/16
B’s 1 day’s work =1/12
C’s 1 day’s work =1/4-[1/16+1/12] = [1/4 - 7/48] = 5/ 48
So, C alone can do the work in 48/5 = 9 (3/5)